REB data shows demand at 7:00 pm on Monday was 10,235 MW while supply was 7,338 MW. At 8:00 pm, demand increased to 10,447 MW with a supply deficit of 2,414 MW.
Under the directions of PDB, coordination of power distribution among distribution companies is done through the National Load Despatch Center (NLDC) of PGCB. A recent supply plan shows that two distribution companies in Dhaka—Desco and DPDC—have been exempted from load-shedding, while the remaining five distribution companies outside Dhaka have been directed to share the load-shedding burden equally.
In Chattogram, electricity is reportedly interrupted five to six times a day, with each cut lasting between half an hour to an hour. The situation is even worse in rural areas.
Lohagara upazila health and family planning officer Iqbal Hussain said it was becoming difficult to maintain normal health services due to load-shedding.
Engineer Noor Mohammad, senior general manager of Chattogram Palli Vidyut Samiti-1, said that his area is getting 30 to 40 percent less electricity than the requirement on a daily basis.